The Project Manager is creating an estimate for a housing development. This is something for which he is quite experienced. The client needs the estimate in four hours. Which of the following types of estimates make the most sense to use?
Question:
Which of the following types of estimates make the most sense to use?
Options:
Analogous
Gut feel
Bottom-up
Parametric
Correct Answer
The Correct Answer for this Question is
Analogous