You are preparing to start the qualitative risk analysis process for your project. You will be relying on some organizational process assets to influence the process. Which one of the following is NOT a probable reason for relying on organizational process assets as an input for qualitative risk analysis?
Question:
Which one of the following is NOT a probable reason for relying on organizational process assets as an input for qualitative risk analysis?
Options:
Studies of similar projects by risk specialists
Risk databases that may be available from industry sources
Review of vendor contracts to examine risks in past projects
Information on prior, similar projects
Correct Answer
The Correct Answer for this Question is
Review of vendor contracts to examine risks in past projects