Which one of the following is NOT an aim of the change management process?

Which one of the following is NOT an aim of the change management process?

Question:

Which one of the following is NOT an aim of the change management process?

Options:

To ensure the impact of changes are understood

To ensure that changes are recorded and evaluated

To ensure that all changes to configuration items (Cis) are recorded in the configuration management system (CMS)

To deliver and manage IT services at agreed levels to business users

Correct Answer

The Correct Answer for this Question is

To deliver and manage IT services at agreed levels to business users