Which one of the following is NOT an output of the risk response planning?

You are the project manager of the NHH project for your company. You have completed the first round of risk management planning and have created four outputs of the risk response planning ActualTests.com process. Which one of the following is NOT an output of the risk response planning?

Question:

Which one of the following is NOT an output of the risk response planning?

Options:

Risk register updates

Organizational process assets updates

Project document updates

Risk-related contract decisions

Correct Answer

The Correct Answer for this Question is

Organizational process assets updates