You are the project manager of the NHH project for your company. You have completed the first round of risk management planning and have created four outputs of the risk response planning ActualTests.com process. Which one of the following is NOT an output of the risk response planning?
Question:
Which one of the following is NOT an output of the risk response planning?
Options:
Risk register updates
Organizational process assets updates
Project document updates
Risk-related contract decisions
Correct Answer
The Correct Answer for this Question is
Organizational process assets updates