Wendy is about to perform qualitative risk analysis on the identified risks within her project. Which one of the following will NOT help Wendy to perform this project management activity?
Question:
Which one of the following will NOT help Wendy to perform this project management activity?
Options:
Project scope statement
Risk management plan
Risk register
Stakeholder register
Correct Answer
The Correct Answer for this Question is
Stakeholder register