Which one of the following will NOT help Wendy to perform this project management activity?

Wendy is about to perform qualitative risk analysis on the identified risks within her project. Which one of the following will NOT help Wendy to perform this project management activity?

Question:

Which one of the following will NOT help Wendy to perform this project management activity?

Options:

Project scope statement

Risk management plan

Risk register

Stakeholder register

Correct Answer

The Correct Answer for this Question is

Stakeholder register