Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?

Monitor and Control Risks

Plan Risk Management

Perform Qualitative Risk Analysis

Perform Quantitative Risk Analysis

Correct Answer

The Correct Answer for this Question is

Perform Qualitative Risk Analysis

Explanation

The Question – Which process? has been answered correctly and answers for the question is Perform Qualitative Risk Analysis

More about these Exams

These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.

We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.

you can find more here at Certout

Feel free to contact via comment or email.

Happy Learning

Cheers, Team Certout

Leave a Comment