Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?

Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?

Question:

Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?

Options:

Initiating

Planning

Executing

Closing

Correct Answer

The Correct Answer for this Question is

Executing

Leave a Comment