Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

Question:

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

Options:

Cost baseline

Cost forecasting

Cost variance

Cost budgeting

Correct Answer

The Correct Answer for this Question is

Cost budgeting