Which process involves aggregating the estimated costs of the individual schedule activities or work packages?
Question:
Which process involves aggregating the estimated costs of the individual schedule activities or work packages?
Options:
Cost baseline
Cost forecasting
Cost variance
Cost budgeting
Correct Answer
The Correct Answer for this Question is
Cost budgeting