Which process involves developing an approximation of the monetary resources needed to complete project activities?
Question:
Which process involves developing an approximation of the monetary resources needed to complete project activities?
Options:
Estimate Costs
Control Costs
Determine Budget
Plan Cost Management
Correct Answer
The Correct Answer for this Question is
Estimate Costs