Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and PerformQuantitative Risk Analysis?
Question:
Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform
Options:
Initiating
Monitoring and Controlling
Planning
Closing
Correct Answer
The Correct Answer for this Question is
Planning