Which project management process is responsible for these actions?

You are the project manager of the GHY Project for your company. You need to complete a project management process that will be on the lookout for new risks, changing risks, and risks that are now outdated.Which project management process is responsible for these actions?

Question:

Which project management process is responsible for these actions?

Options:

Risk planning

Risk identification

Risk monitoring and controlling

Risk analysis

Correct Answer

The Correct Answer for this Question is

Risk monitoring and controlling