You are the project manager of the GHY Project for your company. You need to complete a project management process that will be on the lookout for new risks, changing risks, and risks that are now outdated.Which project management process is responsible for these actions?
Question:
Which project management process is responsible for these actions?
Options:
Risk planning
Risk identification
Risk monitoring and controlling
Risk analysis
Correct Answer
The Correct Answer for this Question is
Risk monitoring and controlling