You are the project manager of the NHH Project for your company and you have completed the risk analysis processes for the risk events. You and the project team have created risk responses for most of the identified project risks. Now, you would like to assign risk owners to the events. Which risk events should have risk response owners?
Question:
Which risk events should have risk response owners?
Options:
Only the risks with a high risk rating
Each agreed-to and funded risk response should have a risk response owner
Each risk that has a risk response should have a risk response owner
Only the risk events that are considered a negative risk event with a high risk rating
Correct Answer
The Correct Answer for this Question is
Each agreed-to and funded risk response should have a risk response owner