Which risk events should have risk response owners?

You are the project manager of the NHH Project for your company and you have completed the risk analysis processes for the risk events. You and the project team have created risk responses for most of the identified project risks. Now, you would like to assign risk owners to the events. Which risk events should have risk response owners?

Question:

Which risk events should have risk response owners?

Options:

Only the risks with a high risk rating

Each agreed-to and funded risk response should have a risk response owner

Each risk that has a risk response should have a risk response owner

Only the risk events that are considered a negative risk event with a high risk rating

Correct Answer

The Correct Answer for this Question is

Each agreed-to and funded risk response should have a risk response owner

Leave a Comment