Which schedule development tool and technique produces a theoretical early start date and late start date?
Question:
Which schedule development tool and technique produces a theoretical early start date and late start date?
Options:
Critical path method
Variance analysis
Schedule compression
Schedule comparison bar charts
Correct Answer
The Correct Answer for this Question is
Critical path method