Which schedule development tool and technique produces a theoretical early start date and late start date?

Which schedule development tool and technique produces a theoretical early start date and late start date?

Question:

Which schedule development tool and technique produces a theoretical early start date and late start date?

Options:

Critical path method

Variance analysis

Schedule compression

Schedule comparison bar charts

Correct Answer

The Correct Answer for this Question is

Critical path method