Which stage of the change management process deals with what should be done if the change is unsuccessful?

Which stage of the change management process deals with what should be done if the change is unsuccessful?

Question:

Which stage of the change management process deals with what should be done if the change is unsuccessful?

Options:

Remediation planning

Categorization

Prioritization

Review and close

Correct Answer

The Correct Answer for this Question is

Remediation planning