Which statement is true for ALL project stakeholders?

Which statement is true for ALL project stakeholders?

Question:

Which statement is true for ALL project stakeholders?

Options:

Internal to the corporate organization

May either affect or be affected by the project

Review the Communication Management Strategy

Support the project

Correct Answer

The Correct Answer for this Question is

May either affect or be affected by the project