Which tool or technique is NOT used for schedule control?

Which tool or technique is NOT used for schedule control?Work performance data is an input to control schedule.

Question:

Which tool or technique is NOT used for schedule control?

Options:

Performance reviews

Project management software

Work performance information

Leads and lags

Correct Answer

The Correct Answer for this Question is

Work performance information