Which tool or technique is NOT used for schedule control?Work performance data is an input to control schedule.
Question:
Which tool or technique is NOT used for schedule control?
Options:
Performance reviews
Project management software
Work performance information
Leads and lags
Correct Answer
The Correct Answer for this Question is
Work performance information