Who provides the inputs for the original estimates of activity durations for tasks on the project plan?

Correct Answer for the Question – Who provides the inputs for the original estimates of activity durations for tasks on the project plan? is given below

Who provides the inputs for the original estimates of activity durations for tasks on the project plan?

Project sponsor

Project manager

Person responsible for project scheduling

Person who is most familiar with the task

Correct Answer

The Correct Answer for this Question is

Person who is most familiar with the task

Explanation

The Question – Who provides the inputs for the original estimates of activity durations for tasks on the project plan? has been answered correctly and answers for the question is Person who is most familiar with the task

More about these Exams

These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.

We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.

you can find more here at mnccertified

Feel free to contact via comment or email.

Happy Learning

Cheers, Team MNCcertified

Leave a Comment