Why would the project manager need to update the WBS after the risk response planning process?

You are the project manager of the GHY Project for your company. You have completed the risk response planning with your project team. You now need to update the WBS. Why would the project manager need to update the WBS after the risk response planning process? Choose the best answer.

Question:

Why would the project manager need to update the WBS after the risk response planning process?

Options:

Because of work that was omitted during the WBS creation

Because of new work generated by the risk responses

Because of risk responses that are now activities

Because of risks associated with work packages

Correct Answer

The Correct Answer for this Question is

Because of new work generated by the risk responses