You are beginning a new project staffed with a virtual team located across five countries. To help avoid conflict in work priorities among your team members and their functional managers, you ask the project sponsor to prepare a____________.Although the project charter cannot stop conflicts from arising, it can provide a framework to help resolve them, because it describes the project manager’s authority to apply organizational resources to project activities.
Question:
You are beginning a new project staffed with a virtual team located across five countries. To help avoid conflict in work priorities among your team members and their functional managers, you ask the project sponsor to prepare a____________.
Options:
Memo to team members informing them that they work for you now
Project charter
Memo to the functional managers informing them that you have authority to direct their employees
Human resource management plan
Correct Answer
The Correct Answer for this Question is
Project charter