You are conducting a stakeholder analysis on your project. Your organization uses an approach to classify stakeholders based on their level of authority and their active involvement in the project.This approach is known as____________Although a number of classification models are available to help prioritize the key stakeholders, the power/influence grid groups stakeholders based on their level of authority or power and their active involvement or interest in the project.
Question:
You are conducting a stakeholder analysis on your project. Your organization uses an approach to classify stakeholders based on their level of authority and their active involvement in the project.
Options:
A power/interest grid
A power/influence grid
An influence/impact grid
A salience model
Correct Answer
The Correct Answer for this Question is
A power/influence grid