You are documenting them as part of your___________.

You are working on the next generation of software for mobile phones for your telecommunications company. While time to market is critical, you know from your work on other projects that management reviews can be helpful and plan to use them on your project. You are documenting them as part of your___________.The project management plan describes how the project will be executed and monitored and controlled. While it contains a number of subsidiary plans, it also contains other items including information on key management reviews for contents, their extent, and timing to address open issues and pending decisions.

Question:

You are documenting them as part of your___________.

Options:

Governance plan

Change management plan

Performance reviews

Project management plan

Correct Answer

The Correct Answer for this Question is

Project management plan