Correct Answer for the Question – You are managing a major international project, and your contract requires you to prepare both a project plan and a quality management plan. Your core team is preparing a project quality management plan. Your first step in developing this plan is to______________ is given below
You are managing a major international project, and your contract requires you to prepare both a project plan and a quality management plan. Your core team is preparing a project quality management plan. Your first step in developing this plan is to______________
Determine specific metrics to use in the quality management process
Identify the quality standards for the project
Develop a quality policy for the project
Identify specific quality management roles and responsibilities for the project
Correct Answer
The Correct Answer for this Question is
Develop a quality policy for the project
Explanation
The Question – You are managing a major international project, and your contract requires you to prepare both a project plan and a quality management plan. Your core team is preparing a project quality management plan. Your first step in developing this plan is to______________ has been answered correctly and answers for the question is Develop a quality policy for the project
More about these Exams
These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.
We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.
you can find more here at Certout
Feel free to contact via comment or email.
Happy Learning
Cheers, Team Certout